Electric Vehicle Charging Station Permits
Electric Vehicle Charging Station Permitting Checklist
This checklist contains the technical aspects of EVSE installations and is intended to help expedite permitting and use for electric vehicle charging.
All permit applications for EV charging station installations must include the following documentation and adhere to National Electrical Code (NEC) standards:
Required Documentation
✅ Contractor Information
Name, license number, and contact details
✅ Job Address
Full site address where the EV charger will be installed
✅ One-Line Diagram
Electrical schematic showing system layout and components
✅ Existing Electrical Service Size
Amperage of the current service panel
✅ Site Plan
Visual layout of charger location on the property, showing distances, access, and obstructions
✅ Charging Equipment Specifications
Manufacturer’s cut sheet including model number and technical data
✅ Engineered Stamped Report (if required)
Structural or electrical engineering analysis depending on system size or mounting method
✅ Ballard/Vehicle Protection (if applicable)
Details on protective bollards or barriers
✅ Load Calculations
Required for systems sized at 7,200W (7.2 kW) or higher
Electrical Code (NEC) Requirements
✔️ Dedicated Circuit
EV charging equipment must be on its own branch circuit
✔️ Grounding
Proper grounding must be shown on the electrical plan
✔️ GFCI Protection
Required if the charger is located in a wet or outdoor location
______________________________________________________________________________________________________
Electric Vehicle Charging Station Permit Application
Please be prepared to include information related to permitting and installation of electric vehicle chargers/electric service equipment (EVCS/EVSE) in your application for an electrical and/or building permit. Once all required documentation has been uploaded, the review process will begin. This permit will be reviewed by planning and building. Once all reviews are complete, the customer will be notified via email and will be able to pay fees. As soon as fees are paid, the permit will be issued.
Click HERE Version Options Electric Vehicle Charging Station Permits Headline to fill out the application.
Note: Incomplete applications may delay review and approval. Please verify all requirements before submitting your permit.
Have questions? Contact the Building Department at 303-655-2017 or 1stop@brightonco.gov.