Brighton Colorado Utilities Homepage
Search

Water Treatment Plant Project

The City of Brighton is embarking on its most ambitious water project to date to improve and expand its water treatment plant (WTP). Faced with the immediate challenge of meeting reverse osmosis brine discharge permit requirements, the City is also investing in improvements to increase reliability and capacity to support population and development growth. The City’s current water treatment plant is nearing the end of its lifespan at more than 25 years old and does not have sufficient capacity to meet the water needs of a growing City. The new WTP will have capacity to produce 20-million-gallons of water per day (MGD). This increased capacity, along with the City's other water sources, is anticipated to serve current customers and growth through 2045. The cost of construction for the project is approximately $167 million.

For the latest updates on the project, please visit the City of Brighton's YouTube channel.

Live Video of Brighton's new Water Treatment Plant Construction

Key Dates

  • City Council approves design of a new WTP; awarded to Brown & Caldwell: November 2021
  • City Council approves design of a new WTP; awarded to Brown & Caldwell: November 2021
  • First reading of Ordinance for WTP Fee: May 17, 2022
  • Final reading of Ordinance for WTP Fee: June 14, 2022
  • Groundbreaking for WTP: July 26, 2022
  • Grading/Earthwork: August 2022
  • Foundations, walls and roofs: December 2022 - June 2025
  • Installation of final treatment process tanks: May 2025
  • Administration building construction complete: August 2025
  • Electrical equipment delivery complete: December 2025
  • Start-up and Commissioning begins: July 2026 

Target substantial completion date (operational facility): February 1, 2027

Target final completion date: June 1, 2027

Design Videos and Photos:

Image2
Image1
Image3
Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow